BRATTLEBORO, Vt., Sept 12 (Reuters) - Power company Entergy
faced off against the state of Vermont in federal court on
Monday to fight a landmark effort to force the closure of its
aging nuclear power plant.
In the first day of a three-day trial to determine the fate
of the Vermont Yankee plant, Entergy's lawyers said Vermont
politicians had infringed on the role of the federal Nuclear
Regulatory Commission, which monitors the nation's 104
commercial power reactors.
New Orleans-based Entergy in April sued the state and Gov.
Peter Shumlin in U.S. District Court, saying Vermont violated
terms of Entergy's deal to buy the reactor in 2002 by giving
politicians the power to shut it.
At issue is a law passed by the Vermont General Assembly in
2006 that New Orleans-based Entergy said put Vermont Yankee's
fate in the hands of elected officials rather than the state
utility regulator, the Public Service Board.
The 620-megawatt (MW) Vermont Yankee plant produces almost
enough electricity to power the entire state. For years, Gov.
Shumlin has spearheaded opposition to the reactor, saying the
39-year-old facility in Vernon, Vermont about 110 miles
northwest of Boston is no longer safe.
Local resistance to the plant hardened after leaky pipes
seeped radioactive material into the groundwater in 2010. If
Vermont succeeds, it would be the first U.S. state to shut a
nuclear power plant that had received an extended operating
permit from the NRC.
In opening remarks to Judge J. Garvan Murtha Entergy said
Vermont had wrongly taken on the role reserved for the federal
government in seeking to rule on the safety of the plant.
"The Atomic Energy Act preempts any effort to shutdown
Vermont Yankee for reasons of nuclear safety," Entergy lawyer
Kathleen Sullivan said.
The trial started on the day an explosion at a French
nuclear waste site killed a worker, and six months after an
earthquake in Japan triggered the world's worst nuclear
accident in 25 years and raised new doubts about the safety of
the technology,
While the trial is set to last three days, a ruling is not
expected until the late September or early October.
Lawyers for Vermont have argued that the state has long
consulted with federal regulators on plant safety. They sought
to show they were not interfering with the NRC's role as the
U.S. nuclear regulator.
Instead, they sought to show Entergy had not been an honest
partner to the state and was unfit to run the plant that the
company bought for $180 million in 2002.
Vermont Assistant Attorney General Scot Kline said
Entergy's recent effort to split off several of its nuclear
plants, including Vermont Yankee, into a separate company, had
shown it was more concerned with profits than safety,
Entergy eventually retreated from its plan to create a
stand-alone nuclear power company in the face of resistance
from states and some of its investors.
Kline said the state effort to shut the plant "supports the
legislature's goal of building a sustainable energy system in
Vermont."
Last year, Vermont's state Senate voted in favor of
shutting the plant when its license runs out.
Entergy, the No. 2 nuclear power operator in the United
States, said that measure invalidated the company's 2002
agreement with Vermont to seek permission from state regulators
-- in addition to national regulators -- before operating the
plant beyond March 21, 2012, when its original 40-year license
was to expire.
Entergy has said the right to assess the plant's safety
lies solely with the federal Nuclear Regulatory Commission,
which this year granted it a license extension for 20 years.
The NRC has never denied an application to extend a
license, having already renewed licenses for 71 of the nation's
104 reactors which provide about a fifth of the country's
power.
Most of the more than two dozen reactors that have already
retired in the United States were decommissioned primarily
because upgrades and repairs were too expensive to keep them
running. The last U.S. power reactor to exit service was
Millstone 1 in Connecticut in 1998.
Entergy, which is also battling efforts in New York to shut
its Indian Point nuclear power plant, says it would prefer to
negotiate deals with the states to improve plants and keep them
in operation rather than fight lengthy legal battles.
Entergy CEO Wayne Leonard told an audience of financial
investors last week that he was more interested in working a
deal than fighting this out in the courts. "It's never over if
you go through the courts."
RENAISSANCE
The global nuclear industry has experienced a renaissance
over the last decade as developing nations sought to meet
growing power demands and raise living standards. More than 60
new reactors are under construction around the world, according
to the World Nuclear Association.
However, construction of new reactors in many developed
nations has stalled. Some countries like Germany have sped up
plans to phase out their existing nuclear fleets following the
Fukushima accident in Japan earlier this year.
The case is Entergy Nuclear Vermont Yankee, LLC et al v.
Shumlin et al, U.S. District Court for the District of Vermont,
No. 11-00099.
For the plaintiffs: Kathleen Sullivan of Quinn Emanuel
Urquhart & Sullivan.
For the defendants: Justin Kolber, Special Assistant
Attorney General.
(Reporting by Zach Howard; Additional reporting by Scott
DiSavino and Matt Daily)
Follow us on Twitter: @ReutersLegal